Timeline of a short repair

It only took 6 hours to complete the work!

It only took 6 hours to complete the work!

9:30am: The vessel SPES (Ro-Ro) was berthed at Car Terminal in Piraeus on 14/7/2018

9:45am - 4:00pm: Turbomed’s expertized technicians were boarded on vessel and started the process of Overhauling-Maintenance of Turbocharger VTR454-11 as follows:

Dismantling of Turbocharger, cleaning all the dismantled parts, inspection measurements, replacement of Gas Inlet Casing, Nozzle Ring and Sealing Bushes, reassembling of all the dismantled parts, final assembling, checking and reporting of all important clearances.

We remain open in August 2018

We would like to inform you that we will be at your disposal throughout August, providing you turbocharger services 24/7 at any place around the world.

Our priority is to serve and support you efficiently whenever is needed.